7329 – Reconstruction of the buildings SO 654/1-02 and SO 320/1-22

country / location Czech Republic, Dukovany
client ČEZ
construction period 07/2015-11/2016
role of PSG turn-key delivery

Brief description of the project

The project is divided into several phases lasting through the years 2015 and 2016. The first phase includes reconstruction of the main entrance. Before the works start it is necessary to establish a temporary gatehouse and to provide temporary safety measures for the building site. The aim of the reconstruction is increasing the security of the technological equipment. The following phase will be the reconstruction of the inner security barrier.