Extension of the production capacity of the company Parker-Hannifin

country / location Czech Republic / Sadská
client Parker-Hannifin s.r.o.
construction period 05/2016 – 11/2016
role of PSG turn-key delivery

Brief description of the project

The project includes extension of two existing production halls, transfer depot, new supply network, relocation of liquid nitrogen reservoir, and minor plant alterations. The production halls are made of pre-cast concrete structure, cladded with sandwich panels and the typical roof structure, i.e. roof sheet, insulation and foil.

The most demanding part of the project will be connection of the existing and newly built halls under full operation. The production of the company should not be interrupted or contaminated.